Lean & Sustainable Factory 2023
Automatic Warehouse for GLT’s
Logistics
-
Scroll for measure details
-
Automatic Warehouse for GLT’s
Area
Logistics
Implementation date
March 2023
Cilck Play to start the video
0:00
01
Before
Manual Warehouse
- All GLT's stored in block storage.
- Inefficient space usage
- External Warehouse needed to store material
02
After
Automatic Warehouse
- Full automation with narrow aisles and shelvestorage
- Smart Warehouse Management System connected to equipment and LOGIS
- Higher storage capacity
- Increased productivity
Project figures | |
|---|---|
Investment | 4,2 Mio € |
Saving | 0,9 Mio € |
Results/improvements | Increase of warehouse positions: external warehouse capacity no longer required; less shelve damages; reduced handling and increased integrity |
4,2 Mio €
0,9 Mio €
Increase of warehouse positions: external warehouse capacity no longer required; less shelve damages; reduced handling and increased integrity