Lean & Sustainable Factory 2023
Framing capacity improvement
Bodyshop
-
Value Stream Management
Scroll for measure details
-
Framing capacity improvement
Area
Bodyshop
Implementation date
2023
Before
Cycle time 68’ / 45 jph
- Framing 3 is the Bodyshop bottleneck
- Stations near the 68’
After
Cycle time 66’ / 50 jph
- Increase Framing 3 capacity by reducing the cycle time:
- Improve robot to avoid anticollision protections.
- Optimization of “Bursten” polishing laser seam.
- Change and optimization of blades for tip-dressing.
- Optimization of welding parameters.
Project figures | |
|---|---|
Investment | NA |
Saving | NA |
Results/improvements | Capacity increase |
NA
NA
Capacity increase