Lean & Sustainable Factory 2023
DK80 | Cycle time improvements
Assembly
Decking
Scroll for measure details
-
DK80 | Cycle time improvements
Area
Assembly
Zone
Decking
Implementation date
2022
01
Before
- DK80 lift table travels up and down to deliver the frame to next station.
- Course distance of 800 mm
02
After
Lower DK80 table only the necessary to allow the exit movement of the frame from DK 80 to DK 85 (less 250 mm of stroke)
Project figures | |
|---|---|
Investment | 13 T€ |
Saving | 4 sec. |
Results/improvements | Cycle time reduction in DK80 of 4 seconds resulting from less travel movement from the table |
13 T€
4 sec.
Cycle time reduction in DK80 of 4 seconds resulting from less travel movement from the table