Lean & Sustainable Factory 2023

Primer over repitch

Paintshop

Primer

Capacity increase

Scroll for measure details

Area

Paintshop

Zone

CR Primer

Implementation date

2023

01

Before

  • With MPV minimum distance between bodies 579 cm

887 units/day (93% up time)

Minimum process time 150ºC, 14min
Cycle time 1,26 min / 47 j/h

02

After

  • EOP of MPV allow to shortage distance between bodies by removing 2 links. Maintain same speed, cycle time

934 units/day (93% up time) normal run, up to 960 with tag relief  in primer prep.

Same speed and cycle time 1,26 min. Minimum process time 150ºc, 14min. 50 j/h

 

Project figures

Investment

0 €

Saving

-

Results/improvements

Productivity/ capacity increase

0 €

-

Productivity/ capacity increase