Lean & Sustainable Factory 2023
Primer over repitch
Paintshop
Primer
Capacity increase
Scroll for measure details
-
Primer over repitch
Area
Paintshop
Zone
CR Primer
Implementation date
2023
01
Before
- With MPV minimum distance between bodies 579 cm
887 units/day (93% up time)
Minimum process time 150ºC, 14min
Cycle time 1,26 min / 47 j/h
02
After
- EOP of MPV allow to shortage distance between bodies by removing 2 links. Maintain same speed, cycle time
934 units/day (93% up time) normal run, up to 960 with tag relief in primer prep.
Same speed and cycle time 1,26 min. Minimum process time 150ºc, 14min. 50 j/h
Project figures | |
|---|---|
Investment | 0 € |
Saving | - |
Results/improvements | Productivity/ capacity increase |
0 €
-
Productivity/ capacity increase