Lean & Sustainable Factory 2023

VPL.e

Assembly

-

Vehicle Prioritization & Location exterior

Scroll for measure details

  1. Vehicle Prioritization & Location exterior

Area

Assembly

Implementation date

June 2023

Click Play to start the video

01

Before

  • No external parking traceability
  • Manual counting on the exterior
  • Counting and analysis loops done by 1 technician
02

After

  • External park stations mapping & coding with thresholds & color codes with an online visualization via webpage
  • Clear visualization & identification of the location of each car and real-time prioritization and traceability in external parks

Project figures

Investment

40 T€

Saving

128 T€/y

Results/improvements

Positive impact on main KPI’s: MDLZ, Schleppe, Program Achievement. Park reconfiguration with ≈ 200 extra slots

40 T€

128 T€/y

Positive impact on main KPI’s: MDLZ, Schleppe, Program Achievement. Park reconfiguration with ≈ 200 extra slots